What Is a Change Order in a Remodel? Ours Is Cost + 25%

A change order is a written change to your signed remodel scope. Ours is priced at cost plus 25%, in writing, before the work continues.

The short answer

A change order is a written change to the scope you signed. It adds work or swaps one thing for another after the job is priced. At Salvation Home Remodeling a change order is priced at cost plus 25%. You get the number in writing before the work continues.

On this page
  1. What a change order is
  2. What causes a change order
  3. What our change orders cost
  4. How a change order goes, step by step
  5. Change order or not: common cases
  6. How to keep change orders low
  7. Where you will see this rate
  8. How to get a written scope
  9. Questions homeowners ask

Change orders are a normal part of general contracting, and most homeowners hear the term for the first time in the middle of a job. This page shows what one is, what causes one, what ours costs, and how to keep the count low.

Planning a remodel? Tell us what you want to change. 3 quick taps, then we call you.

Plan my remodelSee our work

Key points
  • A change order changes the signed scope. It is priced and put in writing before the work continues.
  • Our rate is cost plus 25%.
  • Two things cause one: something hidden that the demo finds, or a change you ask for.
  • A permit is not a change order. Permits are billed at cost and are not in the quote.
  • A clear written scope is the best way to keep change orders low.

What a change order is

Your quote is a price for a list of work. That list is the scope. When you sign, the scope and the price are set.

A change order is the paper that changes that list after you sign. It says what changes and what the change costs. It is priced and approved before the work happens. Every time.

AI illustration of an old cast iron drain line under an opened bathroom floor
AI illustration. Not a photo of our work. A drain line under the floor is one thing a demo can find.

What causes a change order

There are two causes.

Something hidden. No one can see inside a wall or under a floor before it is open. Here is the example we give on our bathroom page. Drain lines in older homes are commonly cast iron, and cast iron does not last forever. We look at the drain before we price the job, not after the demo. But if a line has to be cut out and replaced once the floor is open, that is a change order at cost plus 25%. You get the number in writing before we do the work.

A change you ask for. You add work, or you swap one material for another, after the scope is signed. That is your right. It is also a change to the price, so it goes on paper first.

What our change orders cost

Our change orders are priced at cost plus 25%. Cost is what the changed work costs us. We add 25% to it.

Here is the math with made-up numbers. If the added work costs us $1,000, the change order is $1,250. These two numbers only show how the formula works. They are not a price for any real job.

We print this rate on our site because you should know it before you sign, not after the floor is open.

How a change order goes, step by step

  1. We stop. The extra work does not start.
  2. We show you. If we found something, you see photos of it.
  3. We price it in writing. The price is cost plus 25%.
  4. You approve it. The extra work waits for your yes.
  5. The work continues.

The order of these steps does not change. The price comes before the work.

AI illustration of tile samples and a tape measure on a work table
AI illustration. Not a photo of our work. A swap of materials after you sign is a change order too.

Change order or not: common cases

Not every extra cost is a change order. This table shows where the line is.

The caseIs it a change order
The demo finds a failed drain line under the floorYes. Cost plus 25%, in writing, before the work continues.
You add or swap work after you signYes. Same rate, same steps.
The permitNo. Permits are billed at cost. They are not in the quote.
Kitchen appliancesNo. You buy them and we install them.
Work that is in the written scopeNo. It is in your price.
Permits and appliances are outside the quote from day one. They are not a surprise and they are not a change order.

How to keep change orders low

You cannot remove every unknown. You can remove most of the avoidable ones.

  • Get the scope in writing. A vague scope leaves room for surprises. Read what a written scope protects you from.
  • Choose your materials before the job starts. A swap after you sign is a change order.
  • Know which parts travel together. If all the lower cabinets are replaced, the countertops must be new too. New cabinets or new countertops usually take the old backsplash out with them. We say this up front, so it is in the scope from the start.
  • Ask what is not in the quote. Permits are billed at cost. Appliances are yours to buy. More items are in our guide to what a remodeling quote does not include.

One more date to know. A quote is good for 30 days.

Where you will see this rate

These cost guides state the same rate. If you are pricing a room, start with the guide for that room.

How to get a written scope

It starts with a free walk-through. We look at the house, we write the scope, and we price it. The quote is good for 30 days.

To set a walk-through, call or text 817-210-7117.

Questions homeowners ask

What is a change order in a remodel?

It is a written change to the scope you signed. It adds work or swaps one thing for another, and it states the price of the change.

How much does a change order cost?

Ours are priced at cost plus 25%. You get the number in writing before the work continues.

Can a remodel finish with no change orders?

Yes, it can. A change order only happens when the scope changes. A clear written scope and a careful walk-through lower the chance. No one can see inside a wall before it is open, so no one can promise zero.

Is a permit a change order?

No. Permits are billed at cost and are not in the quote. You know that before you sign.

Do I approve a change order before the work is done?

Yes. A change is priced and approved before the work happens. Every time.

Pictures marked “AI illustration” are made with AI. They are not photos of our jobs. See real photos in our project gallery.

Planning a remodel? Tell us what you want to change. 3 quick taps, then we call you.

Plan my remodelSee our work

Service Area Map
Job costs tracked with Job Cost Pro — built by our owner.

Privacy Policy

Salvation Home Remodeling
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.